PROJECT LOCATION: PERM - RUSSIAN FEDERATION
ARCHITECTURE: UMO ARCHITECTURE LTD.
CONTRACTOR: YENIGUN CONSTRUCTION CO.
PROJECT DESCRIPTION: The total project is 35,000 m2. Concrete and static project services were provided. 3-Block has occurred. The structural system is concrete. There are x9.0m 9.0mm axle openings. Brought the project to be greater emphasis on front-line consoles openings.

PROJECT LOCATION: PERM - RUSSIAN FEDERATION
ARCHITECTURE: Your ARCHITECTURE LTD. STI.
CONTRACTOR: SUMMA Inc.
PROJECT DESCRIPTION: The total project is 20,000 m2. 3-Block has occurred. 1. block of 4-storey shopping center, 2 Block 1-storey hypermarket, 3. 4-storey business center is planned as a block. The first modern shopping center in the city of Perm.
Single pile and raft foundation system is essential. Hypermarket more space is covered with roofing system. Each block is separated diletasyonla. In general, axle openings 6.0 mx 6.0m, 6.0 mx is 12.0M.

Progenic LOCATION: Chisinau - Moldova
DESIGN: SIZE OF ARCHITECTURE
CONTRACTOR: SUMMA - FIBA Inc.
PROJECT DESCRIPTION: The total project is 70,000 m2. Concrete and static project preparation services were provided. Diletasyonlarla structure is divided into 3 separate blocks ... Is a shopping center. Basement and ground floor + 3 floors consists of 2 pieces. Basic system has been constructed in zone 1 waffle radyedir.Yapının Degree earthquake zone. For this reason, attention has been given carrier placement of concrete rfc wall system.

PROJECT LOCATION: PERM - RUSSIA
ARCHITECTURE: YENIGUN CONSTRUCTION CO.
CONTRACTOR: YENIGUN CONSTRUCTION CO.
PROJECT DESCRIPTION: The total project is 25,000 m2. Static's second largest shopping mall in the city of Perm and the concrete prepared. Pile foundation system as a single carcass projerlendirilmiştir temeldir.Betoanrme. Plaque waffle slab system. Column headings are the effect of the stapling. Axles 8.40 m x 8.40 m x and y directions. The building is 138.00 m and no expansion joints long way.

PROJECT LOCATION: PERM - RUSSIA
ARCHITECTURE: YENIGUN Inc.
CONTRACTOR: YENIGUN Inc.
PROJECT DESCRIPTION: The total project is 14,000 m2 .... Housing as a projected 22 floors. Building structural system designed by Russian architects concrete. Building long-consoles, and indented, protruding façade is interesting in terms of flat plate system.

Progenic LOCATION: EKATERINBURG - RUSSIAN FEDERATION
ARCHITECTURE: YENIGUN CONSTRUCTION CO.
CONTRACTOR: YENIGUN CONSTRUCTION CO.
PROJECT DESCRIPTION: The total project is 82 000 m2. Diletasyonla is divided into 3 separate blocks ... 1. and 2 Diletasyon 2-fold and 6-fold Shopping Center in the basement, 3 Block 13-storey business center.
The structural system is designed as a reinforced concrete skeleton. Wheel openings are 8.50 x 8.50 m. Slab thickness 25 cm and the overall column size is 80 cm x 80 cm. Column headings are used in order to eliminate the effects of punching them. Was designed by the British architectural firm Chapman Taylor facades of the building.
The floor of the building sits showed that feature different characters. For this reason, the basic structure of the raft and pile foundations of a singular combination solved

PROJECT LOCATION: PERM - RUSSIAN FEDERATION
ARCHITECTURE: Your ARCHITECTURE LTD. STI.
CONTRACTOR: ANT BUILDING Procons Ltd. Sti.
PROJECT DESCRIPTION: The total project is 35,000 m2. Diletasyonla is divided into 3 separate blocks ... 1. Stage is a continuation of the shopping center. In general, the blocks carrier systems composed of 4 floors concrete. Basic structure of the 35x35 cm, h = 12 m radyedir prefabricated pile. The new tram line from the junction of the old block to block, go through the tunnel created in the building for 16 m span. Located in front of the middle block was prepared steel construction sphere.

PROJECT LOCATION: Krasnayarsk - RUSSIAN FEDERATION
ARCHITECTURE: ARCHITECTURE OFFICE ARTUSHYAK
CONTRACTOR: YENIGUN CONSTRUCTION CO.
PROJECT DESCRIPTION: The total project is 55,000 m2. Krasnayarsk contained in Irkutsk in Russia is experiencing the most severe winter conditions are on the edge of the river Yenisei.
Krasnayarsk structure with reinforced concrete structural system of the city's first and most modern structure. Floor openings openings 9.0 mx 12.0 m. Kalınlaştırmalar preventing early colon stapling done. Single pile foundation on the basic structure.

PROJECT LOCATION: Perm - RUSSIA
ARCHITECTURE: YENIGUN Inc.
CONTRACTOR: YENIGUN Inc.
PROJECT DESCRIPTION: The total project is 12 500 m2 .... Lenin street in the city of Perm, located on the business and alışmerkezidir. Buildings in the city center, and due to be included in the basement floor level of the existing structures were shoring. Designed as a reinforced concrete skeleton. Cracked reinforced concrete roof slabs, waffle slab floors. Special measures were taken due to the proximity of other buildings the basic structure.

PROJECT LOCATION: ATRYU / KAZAKHSTAN
ARCHITECTURE: Khaldun Ertekin
CONTRACTOR: AHSEL CONSTRUCTION CO.
PROJECT DESCRIPTION: The total project is 18,000 m2 .... designed as reinforced concrete. Raft foundation is built upon.